A short week, but never the less it was not short of excitement. I rented a compact machine for two days to compact the sand in preparation for casting the floor.
We need a total of 6300 cement blocks for the building, and I told the community that they need to produce minimum of 360 blocks per day, using twelve bags of cement. So far they molded about 4300 blocks.
Monday the community did not have money to buy food for the workers so, they were hungry and left at lunch. Tuesday the same and Wednesday, twenty people came, but they were tired and produced only 120 blocks, using only four bags of cement.


There are no signs leading to Airfield Community. From the main road you would not know that anyone live in the bush. An airport was planned for the area, but will probably never be built. Land was available and 400 people settled in the area. They came from the coast, from the north or escaped

Due to the holiday, work was not scheduled for Airfield Community, but they all decided to work anyway. I counted 40 community workers. Foundation blocks were already cemented in the trenches. Women running back and forth, large cement blocks on their heads. "blocks", "mortar", shouting form the site and the women ran to deliver the goods. 